April 30--U.S. Senate
budget writers followed their House counterparts this week with questions about
the rising costs of the mixed oxide fuel plant under construction at Savannah River Site.
In particular, the
projected annual cost of operating the facility -- after it is completed -- has
risen from $156 million to $499 million in just two budget years, according to
a new draft of the 2013 Senate Energy & Water Development Appropriations
bill.
The National Nuclear
Security Administration, an arm of the Energy Department that manages nuclear
weapons programs, "has failed to provide a sufficient justification for
this increase," the report said.
The $4.8 billion MOX
plant is the centerpiece of a plan to dispose of 34 metric tons of plutonium
from dismantled nuclear warheads by blending the material with uranium to make
commercial reactor fuel. The facility is 60 percent complete and scheduled to
open in 2016, with fuel production under way by 2018.The Senate
Appropriations Committee also wrote that it supports NNSA's proposal to abandon
plans for a standalone facility to disassemble plutonium "pits" from
surplus warheads but questioned the costs that went into planning a facility
that NNSA now says is not needed.
"The Committee
supports NNSA's decision to terminate the Pit Disassembly and Conversion
Facility because of significant cost overruns," the report said.
"However, the Committee is concerned by NNSA's failure to identify
alternatives earlier, before spending $700,000,000 over 13 years and
determining that existing facilities could be used to meet mission needs."
Under the most recent
plan, the process of converting the pits into an oxide form suitable for MOX
feedstock will be conducted using a combination of existing facilities. A final
record of decision on that alternative is expected later this year.
Despite the critical
questions, the Senate appropriations bill recommends fully funding the fiscal
2013 request for $388.8 million in construction funds for the project, just as
the House Appropriations Committee did last week.
House budget writers
also raised questions about the project's costs and asked for an inquiry from
the Energy Department's comptroller general to gauge the accuracy of the cost
projections.
"The Department
is now reporting internally that the total project costs could be understated
by as much as $600 million to $900 million, and that the project will overrun
its projected completion date by months if not years," the committee
wrote.
Kelly Trice,
the president of Shaw AREVA MOX Services,
which is building the plant, said officials are working diligently to find ways
to cut costs or avoid cost increases, but will continue to focus on quality
workmanship and maintaining an excellent safety record.
"Despite these
costs being driven up by the 'nuclear renaissance,' we are about 60 percent
complete with the project and are currently on track to finish in approximately
4 years," he said, in an e-mailed statement.
No comments:
Post a Comment